During the period January-September 2023, the HERACLES team carried out the authorisation procedures for the installation and operation of the MTU pilot unit at the Volos plant.
The HERACLES team worked with its partners on on-site flue gas characterisation and on the methodology for evaluating and technologically qualifying large-scale capture plants, providing data on flue gas properties, detailed stack drawings and exchanging clarifications on the connection of the MTU to the stack.
Bypass pipes have already been installed to feed the MTU.
Visits are currently being planned for an overview of the installation area, as well as for sampling and in situ flue gas analysis.
Join us at the European Cement Decarbonisation Summit 2024 | Oct. 30th – 31st in Hamburg (Germany)
We are excited to announce that the AURORA project, coordinated by SINTEF, will be prominently featured at the upcoming European…